Walking the fall backwardsLowest cover first
-
Downstream cover first
Chamber 01
The lower cover, not the gully everyone points at: it shows whether the run already stands full.
-
Gas test, then levels
Both ends
Gas-tested before anyone leans in; cover and invert levels at both ends, because they are the fall.
-
In against the flow
Upstream travel
The camera climbs against the water, out of the cover already lifted.
-
Code it where it is
Clock reference
Chainage is read off the cable as it pays out; each feature gets a clock reference, 12 the crown, 6 the invert.
-
Stop where the camera stops
Reported, not assumed
Where the camera stops, the report stops: the length beyond goes down as unsurveyed, never as sound.
Grades 1–5Five ways a run stops carrying
A coded feature gets a grade, the grade decides which remedies are on the table, and the remedy decides who signs.
| Gr. | What the water meets on the run | Detail |
|---|---|---|
| 1 | Barrel round, joints closed, full bore to the next chamber.Structural 1 · service 1 | Open |
|
||
| 2 | Hairline crack, slightly open joint, or deposits under five per cent of bore.CR · OJM · DES | Open |
|
||
| 3 | Multiple fractures, roots through a joint, deformation, or deposits to twenty per cent of bore.FC · RI · D | Open |
|
||
| 4 | Broken pipe, pieces displaced, invert missing, a hard obstruction, or running infiltration.B · OB · IN | Open |
|
||
| 5 | Collapse. Bore lost, void over the crown, ground loss, settlement at the surface.X · void confirmed | Open |
|
||
The same stoppage, two different digsGrade against job
The same code at the same grade is a two-hour patch under a driveway and a week of propping under a conservatory floor.
So the grading is written before the quotation: chainages, depth to invert, the surface above each defect.
Where the fall goes slackFall and gradient
A run that silts up every winter is usually not dirty. It is slack, and it was slack on the day it was laid.
Solids drop out of water that has stopped moving, and the bore narrows from the invert up.
Fall and gradient checker
Maguire’s ruleEnter a length and a fall.
- Gradient
- —
- Reference gradient
- —
- Comparison
- —
One in the bore in millimetres over 2.5; what a run is built to comes from its designer.
Rain that never reaches a sewerSurface water
Roof water is the other half of the fall.
Plenty of foul runs around Teynham carry roof water they were never sized for: a downpipe went into a gully that turned out to be foul.
Which gully is which A tracer at the head of the run, watched at the next chamber, settles it.
Taking the roof off that run means sending it elsewhere: a soakaway, a crate, or an agreed surface-water connection.
Order of preference Ground first, watercourse second, sewer last and only on written agreement.
Whether the ground drinks at all is measured, not assumed.
Percolation A pit to the soakaway’s depth, filled and timed three times, slowest used.
Where the roof water goes
One trench, one stormEnter a roof area.
- Inflow over the storm
- —
- Soaks away per metre run
- —
- Trench length needed
- —
- Storage to be held
- —
One storm, one trench. A full sizing repeats it across durations.
Four answers to a run that has stoppedSIC 42990
-
Read
CCTV survey
A coded crawl against chainage, a still per feature, two grades. What a report carries.
-
Close
Patch, line or dig
Three remedies, and conditions on the run that take the choice away. Which a defect allows.
-
Lay
Fall built in
Set out upwards from the connection, bedded to a class, closed by test. Levels and bedding.
-
Join
Sewer adoption
Drawings, levels and calculations that have to agree. What goes in.
One engineer, a camera and a levelling staff. No crew, and no second visit to find the covers.
Survey requests go to the office email with a street address and the cover positions if known.
ExcavationReaching the pipe, and closing the ground again
Reaching a slack or broken length is mostly excavation with a short piece of pipework in the middle. Utility drawings are pulled, the ground swept, trial holes dug by hand.
An opening in a public footway is a permitted street work carrying its own reinstatement specification, and one that fails inspection is dug up again at the opener's cost.
Soft ground is the same sequence in other materials, topsoil kept separate and put back last; how far the sides stand unsupported is the ground around Sittingbourne.
Run A, and the metre the water stopped at0–24 m
Ask the office to look at a runSite survey
What the office needs first is where the run is and what it is doing. Everything else is read on site from the covers.