Three remedies, each with conditions that rule it in and conditions that rule it out, and a survey that decides which.

Sheet 03 · back to the defect schedule

What happens before any remedy is chosenPreparation

Nothing is lined, patched or dug until the run has been cleaned and looked at again. The sequence is fixed, and the remedy is chosen at the end of it rather than at the start.

  1. Clean the bore out Jet and cut

    Deposits are jetted out, scale is cut back and roots are cut to the pipe wall, so what is left is the pipe rather than what was sitting in it.

  2. Survey it again Second log

    A grade 4 obstruction that jets away was a grade 2 service defect wearing a disguise, and only the second survey proves which of the two it was.

  3. Read the wall, not the log Bondable?

    A resin patch will not bond to a greasy or silted wall, a liner will not lie flat over a root ball, and neither will pass a joint standing proud of the bore.

  4. Then choose Patch, line, dig

    Only now is a remedy named, against the run as it stands after cleaning and against the conditions set out at the foot of this page.

Three stages of patch lining shown in section: the packer carrying the resin sleeve positioned over the defect, the packer inflated to press the sleeve against the pipe wall, and the cured patch left in place with the packer withdrawn 1 · packer set to the chainage defect 2 · inflated, resin pressed out 3 · cured, packer withdrawn bore kept
A patch is a short glass sleeve wetted out with resin, carried on an inflatable packer to a chainage read off the same cable the camera used. It cures in the pipe and the packer comes back out; the run is surveyed again before the job is called finished.

Patch lining a single defectLocalised

A patch suits one defect, or two close together, in a pipe that is still round and still on line. The sleeve is cut to length, wetted out, wrapped on the packer, and set to the chainage logged in the survey. It bridges a fracture, seals an open or slightly displaced joint, stops a point of infiltration, and closes the hole a root came through once the root is cut.

What a patch will not do is correct a gradient, re-round a deformed pipe, or hold a length where the host has lost its shape. It also needs an access point close enough to get a packer in, and a run that can be taken out of use for the cure. Where either is missing, the patch comes off the list.

Lining a run end to endFull length

Lining end to end suits a run with defects spread along it, or a run that has to be sealed against infiltration over its whole length. A felt or glass liner is wetted out, inverted or winched in, pressed against the wall and cured, and every lateral that was open before is cut back open from inside afterwards.

Lining also fixes the line it finds. A liner follows the host pipe, so a run laid with a back-fall or a dip keeps both. Those are levels faults, and levels faults are corrected by relaying.

Cutting out and relayingOpen cut

Excavation is the answer when the shape or the position of the pipe is wrong rather than its surface: a collapse, a deformation past re-rounding, a back-fall, a void over the crown, or a connection that has to be made where none exists. It is also the answer when there is no access point to work from.

The hole is set out from the chainage and the measured depth, services are traced and hand-dug to, the sides are battered or supported, and spoil is kept off the dig. The new length is laid to recovered invert levels, bedded and surrounded as the specification requires, tested, and surveyed before the trench is closed. Reinstatement is then its own piece of work with its own standard, in the highway or in a lawn.

Choosing between the threeDecision

The three remedies are not ranked. Each has conditions that rule it in and conditions that rule it out, and the survey is what decides which list a run falls into.

What the survey has to show for each remedy
RemedyRules it inRules it out
PatchOne or two defects at known chainages, host round and on line, access within reach of a packer.Deformation, back-fall, defects spread along the run.
Full-length linerDefects along most of the length, infiltration throughout, host still round and still on line.A run already surcharging, a lost bore, a dip or back-fall.
Open cutCollapse, void, wrong levels, a new connection, no access point to work from.Nothing on the surface can be opened — then the run is lined and the levels fault is recorded as remaining.